-Area-48 Engineering & Technical Service Department-
Project #002
[Project: Bridge Over a Bridge]
Project Goal:
Construct a structurally reliable bridge above SCP-1437 in order to accommodate the needs of future SCP-1437 testing by the Area-48 research department.
Project Staff:
Project Manager: Dr. Smooth
Lead Engineer: Engineer Mercer
Engineering Team: -Awaiting Staff-
Bridge Construction Phase:
03/04/1986 - Dr. Smooth assembled a security team along with Engineer Mercer to stake out and begin assembly of a bridge.
Construction halted due to an attack from an unknown individual.
Phase Ia Incidents
- 1 Foundation Transport Truck Lost to SCP-1437
- 1 Injured Personnel SID Specialist Blueberry
Phase Ib Accomplishments
- Area surveyed and bridge foundation layed out
- Concrete Footings poured and currently curing
Phase II Bridge Rework & Construction:
03/13/1986
-Blueprint reworked due to research report Green Lightning
-Steel supports and attachments made onto footings
-Steel Plateform place onto supports and footings
-Electric crane errected and attached to gaslone generator
-Safety Railing attached to platform
Platform Test Phase:
-Platform constructed and safety regulations inspected
-Crane in operational status
-Project Complete Ready for use
Notes:
Engineer Mercer has been assigned as lead engineer to complete this project.
-Dr. Smooth